Inch Cape
1,080 MW offshore wind development with published delivery-package suppliers and a project supplier-registration route. DESNZ records 266.11 MW in Contracts for Difference allocation round AR6. The current contract status and strike price remain unverified.
- Lieu
- Offshore – Scottish Borders (15-22 KM off the east Angus coastline), Offshore, Scotland
- Étape du projet
- Sous Construction
- Capacités
- 1080 MW
- Points de repère
- Turbine installation planned late 2026 to mid-2027; commercial operation targeted 2027. On 20 November 2026 Cadeler’s Wind Mover left Dundee for Inch Cape with nacelles, blades and towers for the first two 15 MW Vestas turbines. Installation and first power are subsequent milestones.
- Vérification des antécédents
- 2026-11-22
REPD applicant; current ownership still to verify
Red Rock Power (ICOL)
Contractors and work packages
- Siemens Energy — Electrical transmission (source du package)
- Iemants (Smulders) — Electrical transmission (source du package)
- Vestas — Turbines (source du package)
- Cadeler — Turbine installation (source du package)
- CWHI (GWSHI) — Monopiles and transition pieces (source du package)
- Dajin Offshore — Monopiles (source du package)
- COOEC Fluor (CFHI) — Jackets and transition pieces (source du package)
- Jan De Nul — Monopile installation (source du package)
- Seaway7 — Jacket installation (source du package)
- Orient Cable — Export cable fabrication (source du package)
- Enshore — Export cable installation (source du package)
- TKF — Array cables (source du package)
- N-Sea — Array cable installation (source du package)
- Port of Montrose — Offshore construction base (source du package)
- Forth Ports — Leith and Dundee marshalling (source du package)
- RJ McLeod — Onshore enabling works; completed 2023 (source du package)
- Careys — Onshore main civil works (source du package)
- Charles Brand — Landfall civil works (source du package)
Opportunités pour les fournisseurs
- Inch Cape supplier registration List your company and capabilities on Inch Cape’s supplier database. The project and principal contractors use the database to identify potential suppliers. Check Energy Pathfinder for individual advertised scopes.
nouvelles connexes
Project sources
- DESNZ REPD T2 2026 — référence 2527
- Publication et méthodologie gouvernementales
- Project / contractor evidence — Undated owner page; checked 2026-10-26
- Project / contractor evidence — Owner construction page; checked 2026-10-26
- Registre trimestriel des projets de DESNZ, référence 2527
- Inch Cape confirms departure of first two turbine sets
- Inch Cape information for suppliers, March 2025
- Inch Cape owners announce financial close