Aureos wins Dungeness A decommissioning contract worth up to £190m

File photograph: Dungeness A power station, Kent, 8 August 2005; not current decommissioning work.

Nuclear Restoration Services has appointed Aureos for a Dungeness A decommissioning contract worth up to £190 million, moving the Kent site into a major heavy-engineering phase.

The award announced on 28 October covers removal of eight boiler units, each weighing around 800 tonnes, alongside associated equipment and infrastructure. It follows four years of enabling works.

A specialist jack-and-slide system will move the boilers. NRS says the completed project will remove approximately one-third of the site’s above-ground structures and reduce its long-term maintenance requirements.

Aureos was selected through a competitive procurement process. The programme includes engagement with local businesses, schools and universities and opportunities for the supply chain, although the release gives no recruitment total.

For nuclear contractors, the award creates a substantial defined delivery scope involving dismantling, heavy handling and site restoration. Completion of this package will be one stage in the wider decommissioning programme, rather than the end of all work at Dungeness A.

Source: NRS and NDA announcement, 28 October 2026.

Explore nuclear jobs.

Image credit: File photograph: Dungeness A power station, Kent, 8 August 2005; not current decommissioning work. Photo: Sandpiper, Wikimedia Commons; released into the public domain by the photographer. Resized and converted to WebP. Original photograph and attribution; licence.

Compiled by Energy People with AI assistance from the linked sources. No interview or on-site reporting is implied.

Share this article
EmailWhatsAppLinkedInFacebookX