ElectraNet begins restoring Eyre Peninsula transmission after storm damages three towers

Illustrative file photograph: a transmission tower at Mardella, Western Australia, 1 December 2024; not Pilgangoora or the Fortescue Green Grid.

By Energy People

ElectraNet says it began progressively restoring transmission services across South Australia’s Eyre Peninsula at 1pm local time on 20 November after a storm damaged three towers between Port Lincoln and Cleve.

In its 3.40pm update, the operator said crews had established an interim solution and were working with SA Power Networks as electricity was restored through the distribution system, which also suffered storm damage.

ElectraNet’s earlier account said the storm interrupted supply to about 24,000 customers at approximately 3pm on 19 November. Local generation was brought online at 9.45pm that evening, restoring power to around 10,000 customers, mainly in Port Lincoln and nearby areas.

The latest statement does not confirm that all customers have been reconnected. ElectraNet says the interim arrangements require ongoing monitoring, with temporary towers and permanent repairs still to follow.

The distinction matters for local businesses: restored transmission availability does not by itself establish that every affected distribution connection has power. This report reflects the operator’s 3.40pm South Australian update on 20 November.

Original source: ElectraNet restoration updates, 19–20 November 2026.