By Energy People
FERC has granted certificates for Targa Resources’ Forza gas pipeline project between New Mexico and Texas, while imposing a stay during the landowner rehearing process.
The 19 November order authorises approximately 36 miles of new 36-inch pipeline from Desert Ram Junction in Lea County, New Mexico, to Wildcat Junction in Winkler County, Texas. The project would offer up to 750,000 dekatherms a day of firm transportation capacity.
Forza’s filing estimates a cost of approximately $183.1 million. The scheme also relies on a capacity lease from Bull Run Pipeline, another Targa subsidiary, to connect Delaware Basin gas supplies with delivery points near Waha.
Precedent agreements with Targa Gas Marketing and Devon Energy cover about 87% of the proposed capacity. FERC accepted the evidence of project need after considering objections from affected landowners, including challenges to demand and environmental assessment.
The certificate is stayed for the 30-day rehearing period. If landowners file timely rehearing requests, the stay can continue while FERC considers them, subject to the limits set out in the order. If no such request is filed, it lifts after the initial period.
Forza must also satisfy environmental conditions, confirm executed firm contracts and obtain written construction authorisation. The approval therefore does not establish that work has started. The order requires the authorised facilities to be available for service within two years.
Original source: FERC order CP26-34-000 and CP26-35-000, issued 19 November 2026.
Explore the Targa Resources profile and oil and gas jobs on Energy People.
Photo: Gas-pipeline inspection-gauge loading and unloading station near Dübendorf, Switzerland. Illustrative technology file photograph, not Forza or Targa equipment. Uploaded January 2006; capture date unconfirmed. Audrius Meskauskas (Audriusa) / Wikimedia Commons, CC BY-SA 3.0. Resized and compressed; same licence retained.