By Energy People.
Wind Mover has moved to the Port of Dundee for turbine-component load-out ahead of the Inch Cape offshore wind installation campaign, according to the project’s 9 November weekly operations notice.
Updated 17 November 2026: Inch Cape’s newer notice, issued on 16 November for the week through 22 November, now expects Wind Mover to arrive at the offshore site and commence operations on or around 18 November. This supersedes the earlier expectation of a start around 16 November. It does not confirm that installation has begun or that the first turbine is installed.
The almost 1.1GW wind farm is being built off the Angus coast. Its programme covers 72 turbines, linking offshore construction with port logistics in Dundee and the project’s marine coordination and construction base at Montrose.
Inch Cape’s turbine-installation notice identifies Vestas as responsible for installation and commissioning. Wind Mover will transport components from Dundee and install the turbines, while commissioning technicians are due to work from Acta Hercules with crew-transfer vessel support.
That notice schedules installation and commissioning activity through September 2027. The timing remains a project programme, rather than confirmation of completion.
Electricity from Inch Cape will travel to a new onshore substation in East Lothian. The wind farm will be operated from a purpose-built facility at Montrose Port.
Primary sources: Inch Cape weekly operations notice, 16 November 2026; Inch Cape weekly operations notice, 9 November 2026; turbine installation and commissioning notice; project overview.