Shell and KUFPEC have confirmed that production has begun at Mina West, adding a new source of gas for Egypt’s domestic market. Their announcements on 15 November mark first gas from the Mediterranean development, three years after its discovery.
Shell expects the project to produce 160 million standard cubic feet a day on a gross basis. That is the forecast for the whole development, rather than Shell’s equity share or a confirmed current production rate.
The field lies in the North East El Amriya concession. A new seven-kilometre pipeline connects it to the existing West Delta Deep Marine infrastructure, routing gas through the Burullus processing facility before delivery into Egypt’s domestic grid.
Shell holds 60% and KUFPEC’s Egyptian subsidiary 40%. Shell identifies Mina West Gas Company as the field’s operating company and dates the final investment decision to 30 June 2025.
The operator credits Subsea7 with engineering and subsea execution, and Baker Hughes with supplying long-lead equipment on an accelerated schedule. It says using existing infrastructure helped shorten delivery.
Sources: Shell Egypt announcement, 15 November; KUFPEC first-gas confirmation, 15 November.