By Energy People
Scottish ministers have granted consent for Muir Mhòr, a floating offshore wind development with capacity of up to 1GW approximately 63km off Aberdeenshire.
The decision, announced on 19 November, covers up to 67 turbines and offshore transmission infrastructure linking the wind farm to the Aberdeenshire coast. Developer Fred. Olsen Seawind must satisfy conditions addressing potential effects on commercial fisheries and providing environmental compensation for seabirds.
The developer places the project off Peterhead and targets electricity production in the early 2030s. It says onshore planning consent is already secured and supply-chain engagement is advancing.
Consent is a major development milestone, but does not establish that construction has started or that a final investment decision has been taken. The next stages will require delivery of the consent conditions alongside the project’s commercial and engineering work.
Original sources: Scottish Government, 19 November 2026; Muir Mhòr project information.
Explore Fred. Olsen Seawind and wind-sector jobs.
Image: illustrative floating-wind file photograph of Hywind Scotland off Peterhead, 22 June 2022; this is not Muir Mhòr. Mike Pennington / Geograph via Wikimedia Commons, CC BY-SA 2.0. Resized; same licence retained.