Norway’s energy regulator NVE has granted a licence for the Moldalsknuten wind project in Sokndal, Rogaland, allowing up to 40 MW of installed capacity.
The decision dated 21 October 2026 permits up to eight turbines, each no more than 200 metres high, within an approximately two-square-kilometre area. The licence runs for 30 years.
The approved works include a roughly one-kilometre 33 kV power line and an access connection to the existing Tellenes wind-farm road. Grid connection will use Tellenes transformer station 2.
NVE estimates generation of up to 92.8 GWh. It says biodiversity impacts are the main drawback and has imposed conditions including management of at least 1.5 square kilometres of nearby coastal heathland.
Eviny says the project builds on roads, grid connections and other existing infrastructure around Tellenes. The licence marks regulatory progress; it is not evidence that turbines have been ordered or construction has begun. The decision can be appealed.
Sources: NVE decision notice, 21 October 2026; Eviny statement.
Compiled with AI assistance from the linked primary sources.
File photograph: Storøy wind farm, Karmøy, Norway, 5 August 2021. Illustrative Norwegian wind infrastructure, not the proposed Moldalsknuten project. Photo: Ryan Hodnett, CC BY-SA 4.0. Source: https://commons.wikimedia.org/wiki/File:Wind_Turbines_-_Karm%C3%B8y,_Norway_2021-08-05_(03).jpg Licence: https://creativecommons.org/licenses/by-sa/4.0/ Resized; same licence applies.