Rezolv Energy has signed financing of up to €367 million for the 292.5 MW Dunarea East wind farm in Romania’s Constanța County, advancing a project scheduled to enter operation in early 2029.
The 6 November announcement identifies a six-lender consortium supported by Denmark’s Export and Investment Fund, EIFO. The European Bank for Reconstruction and Development is among the lenders, with its participation backed by an InvestEU guarantee.
The project combines a Contract for Difference covering 211 MW with a corporate power-purchase agreement involving Ahold Delhaize. These arrangements provide revenue visibility alongside the new debt package.
Rezolv says the financing allows it to proceed into construction. That is a development milestone, not confirmation that the wind farm is generating electricity; the operating date remains a company forecast.
The financing is distinct from the retailer agreement announced a day earlier. It strengthens the funding basis for construction and associated supply-chain work, although the release does not quantify recruitment or announce specific construction awards.
Source: Rezolv Energy, 6 November 2026.