Rosetti Marino has secured a contract worth more than €400 million to modify the Sabratha platform offshore Libya for Mellitah Oil & Gas.
The Italian contractor disclosed the award on 12 November. Its engineering, procurement, construction and installation scope covers new modules, a roughly 200-metre riser bundle, and associated piping, electrical and instrumentation connections.
The modifications will enable Sabratha to receive gas from the WHP-A platform, which is being built under a separate contract. Rosetti says Sabratha will also remotely control WHP-A once the Structure A project is complete.
Engineering and prefabrication will take place in Italy. Offshore installation is expected to require an approximately 18-month marine campaign, with Rosetti responsible for organising the necessary vessel logistics.
Work was due to start immediately following the announcement, with completion targeted for March 2029. That is a contractor schedule, rather than confirmation that the modified facilities are operating.
Mellitah’s shareholders are Libya’s National Oil Corporation and Eni North Africa.
Source: Rosetti Marino announcement, 12 November 2026 (PDF, Italian).