SBM completes Jaguar topside lifts as SEAP II hull work starts

Skarv FPSO with red hull in the Norwegian Sea

SBM Offshore has completed the topside-module lifting campaign for FPSO Jaguar and started construction of the SEAP II hull, according to its 12 November project update.

Jaguar, being delivered for ExxonMobil Guyana, is more than 75% complete. Integration and commissioning continue, with first oil expected in 2027. The FPSO’s planned oil-processing capacity is 250,000 barrels a day; that is design capacity, not current production.

For TotalEnergies’ GranMorgu FPSO, SBM said drydock work on the hull is complete and topside fabrication continues. The project is between 50% and 75% complete, with first oil expected in 2028.

Hull construction for Petrobras’s SEAP II, also designated P-87, has begun at a Chinese yard. Engineering and procurement remain under way, with contractual handover expected in 2030. The companion SEAP I, or P-81, remains in engineering and procurement, targeting handover in 2031.

The milestones mark progress across fabrication, integration and commissioning workloads. They are construction updates, not announcements that the new vessels have entered service.

Source: SBM Offshore third-quarter project update, 12 November 2026.

Explore SBM Offshore’s employer profile and oil and gas jobs.

Illustrative FPSO technology file photograph: Skarv in the Norwegian Sea, 24 July 2016. This is a different vessel outside SBM’s fleet, not Jaguar, GranMorgu, SEAP I or SEAP II, and does not show the reported construction work. Øyvind Knoph Askeland / Norsk olje og gass, via Wikimedia Commons, CC BY-SA 2.0. Resized and converted to WebP; same licence retained.

By Energy People. Compiled with AI assistance from linked sources.

Share this article
EmailWhatsAppLinkedInFacebookX