Smulders wins jacket foundation contract for Germany’s 2GW LanWin2 grid link

Race Bank offshore substation topside and yellow steel jacket transported on the barge Caroline

By Energy People

Smulders has secured a subcontract from Dragados Offshore to fabricate the jacket foundation for LanWin beta, the offshore converter platform forming part of Germany’s 2GW LanWin2 grid connection.

The Eiffage subsidiary announced the award on 16 November. Production will take place at sites in Belgium and Poland, followed by final assembly and load-out in the Netherlands.

Construction activities are scheduled to begin in early 2027, with load-out planned for 2030. These are contractor forecasts; the announcement does not say fabrication has already started.

LanWin2 is part of TenneT’s expansion of its German North Sea transmission infrastructure. The converter platform will collect electricity from offshore wind farms for transmission to the mainland through a high-voltage direct-current connection.

The disclosed package covers the supporting steel jacket, rather than the complete converter platform or the entire grid connection. No contract price or employment total was provided.

Original source: Smulders announcement, 16 November 2026.

Explore Smulders’ company profile and wind jobs.

Image: illustrative offshore-grid fabrication file photograph of the Race Bank ROW01-Z01 substation and jacket aboard Caroline, 5 March 2017. This is not LanWin beta or a Smulders-built structure. Alf van Beem / Wikimedia Commons, CC0 1.0. Resized and compressed.

Share this article
EmailWhatsAppLinkedInFacebookX