By Energy People.
SSEN Transmission has identified Cruchie, north-east of Huntly in Aberdeenshire, as the proposed location for its Strathbogie Hub, advancing site selection for the planned second electricity link from Shetland.
The hub would combine a high-voltage direct-current converter station with a 400kV alternating-current substation. It remains in early development: choosing a proposed site is not planning permission or a construction go-ahead.
In its 17 November update, SSEN says Cruchie emerged as the least constrained option after further assessment and community feedback. Cruchie and Rivestone had both been shortlisted; the company reports that most public feedback opposed development at Rivestone.
Public information events are planned for 7 December at Number 30 in Huntly, 8 December at Scott Hall in Forgue and 9 December at Rothiemay Village Hall, each from 3pm to 7pm. Further feedback opportunities will follow.
The wider Shetland HVDC Link 2 would connect renewable generation on the islands with mainland Scotland and the British electricity network.
Source: SSEN Transmission project update, 17 November 2026.
Explore Power & Utilities jobs.
Photo: Knocknagael substation near Inverness, 19 April 2016. Illustrative Scottish grid file photograph, not Cruchie or the proposed Strathbogie Hub. valenta / Geograph via Wikimedia Commons, CC BY-SA 2.0. Resized and compressed; same licence retained.