By Energy People.
Strike Energy has scheduled grid energisation of its 85MW South Erregulla Power Plant in Western Australia for 20 November, working with Western Power.
In its 16 November announcement, the company said the facility was in the final stages of commissioning. Connection is expected to be followed immediately by Australian Energy Market Operator hold-point testing, forecast to last six to eight weeks.
Strike expects to earn electricity-sales revenue during testing as approved output increases. Full commercial operation remains subject to successful completion of that process; the announced date is a planned connection milestone.
The plant sits beside Strike’s wholly owned South Erregulla gas field and will use gas supplied directly from the wellhead. It has secured capacity credits for its full 85MW, alongside potential revenue from electricity sales.
Capacity-credit payments are due to begin after testing concludes and an interim authority to generate is issued. Strike’s stated capacity revenue for the year ending September 2027 assumes a January 2027 start, so it remains dependent on the commissioning timetable.
Source: Strike Energy announcement, 16 November 2026.
Explore Power & Utilities jobs.
Image credit: Illustrative regional file photograph of Kwinana Power Station, Western Australia, 9 September 2020. This is not South Erregulla or its commissioning. Calistemon / Wikimedia Commons, CC BY-SA 4.0. Resized and converted to WebP; same licence retained.
Explore this story
Companies mentioned
- Energy Market · Live jobs · Projects · News