Uniper plans around €6 billion of growth investment through the early 2030s, with new gas-fired power stations and conversions of existing assets taking the largest share.
Presenting its strategy in London on 16 November, the company allocated roughly 60–70% of planned growth spending to flexible generation. It said about €1.3 billion had already been committed since 2023, with more than 20 projects in execution.
A further 25–30% is intended for its Green Generation business, covering solar, onshore wind, battery storage, pumped storage and additional capacity at existing hydro plants.
Uniper identified about 570MW of solar and onshore wind projects in development and execution across Europe and the UK. It also highlighted the revitalisation of the approximately 160MW Happurg pumped-storage plant and around 50MW of additional hydropower along Sweden’s Ume River.
The company said it had secured around 700MW of grid capacity for data-centre projects in advanced development. That figure describes secured grid capacity, not operating data centres.
The investment programme sets out spending intentions across a portfolio; individual projects remain at different stages of development and execution.
Source: Uniper announcement, 16 November 2026.
Uniper company profile · Explore Power & Utilities jobs.