Woodside says its Scarborough energy project was 99% complete at the end of the third quarter, excluding modifications to Pluto Train 1. Its 21 October report retains a target of a first LNG cargo in the final quarter of 2026.
Gas entered the offshore production facility and trunkline during the quarter. After quarter-end, gas was introduced into the warm end of Pluto Train 2 while commissioning work continued.
Woodside also reported 32% overall completion at Louisiana LNG in the United States, with its first train at 41%. That project continues to target first LNG in 2029.
The updates place the two developments at different stages: Scarborough is approaching its first-cargo milestone, while Louisiana remains a construction programme. Both dates are company targets rather than confirmation that cargoes have already been delivered.
Sources: Woodside third-quarter report, 21 October 2026.
Woodside Energy employer profile · Browse LNG jobs
Energy People news brief. Compiled with AI assistance from the linked sources.
Image: Scarborough’s floating production unit during the May 2025 floatover milestone. Archive project photograph, courtesy of Woodside Energy Ltd and McDermott. Source.
Explore this story
Companies mentioned
- Woodside Energy · Live jobs · Projects · News