Hyme development
Norway · Production achieved
Subsea tieback to Njord A with one producer and one water injector. Original Q1 2013 target retained. Operator states first production 25 February 2013; Norwegianpetroleum records 1 March 2013. Dates conflict and remain separately attributed. Production paused in 2016 during Njord refurbishment and resumed April 2023. Original24million boe recoverable estimate increased to about30million by start-up.
Companies and live jobs
These are the participating companies’ vacancies across their businesses; a project appointment does not establish that every vacancy is for this project.
- Equinor · Live jobs · Projects
Current operator page Hyme section: Equinor42.5%,Vår Energi30%,Harbour Energy27.5%. May2011 snapshot: Statoil35%,Petoro7.5%,GDF Suez20%,E.ON17.5%,VNG2.5%,Norwegian Energy Company17.5%; not current shares.
- Vår Energi · Live jobs · Projects
Current operator page Hyme section: Equinor42.5%,Vår Energi30%,Harbour Energy27.5%. May2011 snapshot: Statoil35%,Petoro7.5%,GDF Suez20%,E.ON17.5%,VNG2.5%,Norwegian Energy Company17.5%; not current shares.
- Harbour Energy · Live jobs · Projects
Current operator page Hyme section: Equinor42.5%,Vår Energi30%,Harbour Energy27.5%. May2011 snapshot: Statoil35%,Petoro7.5%,GDF Suez20%,E.ON17.5%,VNG2.5%,Norwegian Energy Company17.5%; not current shares.
- Nexans · Live jobs · Projects
Umbilical;Q1 2011 award
- NKT · Live jobs · Projects
Flexible risers;Q1 2011 award
- Subsea7 · Live jobs · Projects
Subsea template installation;Q1 2011 award
Project evidence
- Hyme plan, investment and awards
- Operator first-production date and revised reserves
- Regulator production date, suspension and restart; publication date not stated
- Reinertsen Hyme topside award
- Operator Hyme ownership section; publication date not stated