Rhum field development and R3 intervention
United Kingdom · Producing; historical development milestones
Development sanctioned2003; first production December2005. Three-well subsea scheme ties back44km to Bruce. R3 was initially unproductive; intervention recovered equipment and removed an obstruction. R3 first production achieved23August2021. May2020 rig award forecast Q4 mobilisation and approximately70days; environmental statement later reports September2020 mobilisation. These are preserved as forecast versus activity, not exact charter dates. Operator website reports OFAC licence/assurance through28February2027; this is attributed operator information, not a blanket supplier eligibility finding.
Companies and live jobs
These are the participating companies’ vacancies across their businesses; a project appointment does not establish that every vacancy is for this project.
- Serica Energy · Live jobs · Projects
Serica50%; IOC (UK)/RMC50%. Operator reports IOC shares held through Jersey purpose trust sinceNovember2018, with RMC managing its interest; current legal structure not reduced to direct Iranian control.
Project evidence
- Rhum first production and R3 actual milestone
- Current hub and Rhum ownership arrangements
- Current field working interests
- Rig award and forecast R3 intervention duration; indexed primary text
- Operator environmental statement: September2020 mobilisation; indexed primary text