Symra development
Norway · Production achieved
Four-well subsea development tied to Ivar Aasen, with modifications at Ivar Aasen and Edvard Grieg. First oil 3 April2026, announced 7 April. Operator estimates approximately63million boe. Retains original Q12027 production target from June2023 approval.
Companies and live jobs
These are the participating companies’ vacancies across their businesses; a project appointment does not establish that every vacancy is for this project.
- Aker BP · Live jobs · Projects
Aker BP operator 50%, Equinor30%, DNO Norge20% in April2026. June2023 PDO snapshot named Sval Energi instead of DNO.
- Equinor · Live jobs · Projects
Aker BP operator 50%, Equinor30%, DNO Norge20% in April2026. June2023 PDO snapshot named Sval Energi instead of DNO.
- TechnipFMC · Live jobs · Projects
Subsea systems
- Halliburton · Live jobs · Projects
Drilling and wells alliance services; detailed division of work not established
Project evidence
- Production, delivery roles, scope and partners
- First oil on 3 April2026
- Original schedule, partners and joint investment
- Aker BP reserves2024: former name Lille-Prinsen
- Regulator confirms rig drilling/completing Symra on 8 October2025; no personal incident data retained