Hornsea 3

Large offshore wind development in the UK North Sea. Ørsted’s third-quarter 2026 presentation reports 95 turbine foundations and both offshore converter stations installed. It gives 2,852 MW of capacity, puts completion at approximately 40% and forecasts commercial operation in Q4 2027 or Q1 2028.

Location
United Kingdom
Project stage
Under construction
Capacity
2,852 MW in the Q3 2026 investor presentation.
Milestone
95 turbine foundations and the second offshore converter station installed.
Record checked
2026-11-22