Transgrid has been appointed to deliver the Hunter Transmission Project in New South Wales, with Downer disclosing an approximately A$1.1 billion contract for transmission-line works over a three-year construction period.
The 23 November announcements cover a 110-kilometre, double-circuit 500kV line between the Bayswater South and Olney switching stations. EnergyCo says the link will strengthen the state’s transmission backbone and carry generation and storage from the Central-West Orana and New England renewable-energy zones.
Downer expects planning, design and procurement to begin in December 2026, with mobilisation on site during 2027 subject to final approvals. Contract award therefore precedes the announced start of on-site work.
EnergyCo forecasts 900 construction jobs for the project. That is a project-wide estimate, not a statement of vacancies currently open at Downer.
The NSW planning approval dates to July 2026 and includes 115 conditions. EnergyCo says the revised corridor largely follows mining, energy and government land, reducing the number of affected private properties.
Sources: EnergyCo announcement, 23 November 2026; Downer ASX/NZX release, 23 November 2026.