Elements Green has signed a grid connection agreement with TenneT Germany for its proposed 400MW battery-storage plant at Stadorf in Lower Saxony. The developer announced the agreement on 16 November.
The project is designed to store 1,600MWh of electricity, equivalent to four hours at its planned rated output, and connect directly to the extra-high-voltage network.
The agreement follows a separate contract for construction of the connection signed in October. Elements Green says the two arrangements establish the contractual basis for building and subsequently operating the grid link.
Its next steps include detailed connection planning, preparation for construction and coordination with project and technology partners. The announcement does not establish that the battery is operating or give a commissioning date.
Source: Elements Green’s 16 November announcement.
Explore Power & Utilities jobs.
Illustrative file photograph: the battery-storage park at Föhren, Germany, on 10 October 2025. This is not Stadorf or its proposed equipment. Photo: P170 / Wikimedia Commons, CC BY-SA 4.0. Resized and compressed; same licence retained.