First Nordseecluster B foundations arrive at Eemshaven for 900MW wind project

Aerial view of wind turbines at Horns Rev, Denmark.

By Energy People

RWE says the first ten monopile foundations for Nordseecluster B have arrived and been unloaded at Eemshaven in the Netherlands, advancing logistics for the 900MW German offshore wind project.

The 23 November announcement identifies Buss Ports’ heavy-lift terminal as the handling base for 60 foundations during 2026 and 2027. Dajin Heavy Industry is manufacturing and supplying the structures, which average about 81 metres in length and 1,350 tonnes each.

Delivery to port precedes offshore installation: RWE expects foundation installation to begin in 2027, followed by 60 turbines in 2028 and commercial operation in early 2029.

Nordseecluster B forms the second phase of the roughly 1.6GW development north of Juist. The 660MW first phase is expected to be fully operational in early 2027.

RWE holds 51% of the project and Norges Bank Investment Management 49%. RWE is responsible for construction and subsequent operation. The port milestone provides evidence of supply-chain progress without implying that the second phase is already generating electricity.

Source: RWE project announcement, 23 November 2026.

Explore the RWE employer profile and wind-sector jobs.

Illustrative offshore-wind file photograph: Horns Rev, Denmark, viewed from an aircraft on 2 September 2018. This is not Nordseecluster, Eemshaven or the newly delivered foundations. Photo: Hartmut Schmidt, Heidelberg / Wikimedia Commons, CC BY-SA 4.0. Resized and converted to WebP; same licence retained.