Nordex installed 2,021 MW of wind turbines in the third quarter, down from 2,576 MW a year earlier, as customer delays, transport-permit delays and blade-related postponements in Türkiye affected deliveries.
The manufacturer’s 5 November results show 331 turbines installed across 15 countries, compared with 420 in 16 countries a year earlier. Europe accounted for 79% of the capacity installed, with North America making up the balance.
Demand moved in the opposite direction: quarterly turbine orders reached 2,810 MW, up 29.5%. The combined projects and service backlog stood at €19.3 billion at September’s end, against €14.9 billion a year earlier.
For contractors and component suppliers, the figures separate the longer-term workload from near-term installation timing. Nordex attributed the lower turbine-production volume to project scheduling; it did not announce a factory closure.
The company reiterated its 11.5–12.5% full-year EBITDA-margin guidance. That increase was first announced on 15 October, rather than being a new change on 5 November.
Source: Nordex Q3 announcement, 5 November 2026.
Explore the Nordex employer profile and wind-sector jobs.
Illustrative company-equipment file photograph: Nordex N90/2500 turbine at Breitling, Rostock, Germany, 7 September 2006. This historical turbine does not depict the 2026 installations or delays. Schiwago / Wikimedia Commons, CC BY 2.5. Resized.
Compiled by Energy People with AI assistance from linked sources.