Nuclearelectrica has signed a €400m financing agreement with the European Investment Bank for the refurbishment of Unit 1 at Romania’s Cernavodă nuclear power plant.
The agreement, signed on 16 November, is the first of two €400m loans within an €800m financing package approved by the EIB board in July. Nuclearelectrica says the second agreement is due to be signed in 2027.
The company puts the refurbishment’s total value at approximately €3.1bn, excluding financing costs. It plans to combine its own capital with borrowing, with the new loan supporting the construction phase.
Preparatory work includes equipment procurement, infrastructure, contracts and approvals. The project’s main shutdown and refurbishment phase is scheduled for 2027–2030; this financing announcement does not report a new unplanned shutdown.
Nuclearelectrica says the investment is intended to extend Unit 1’s service life by another 30 years and support annual electricity supply of around five million MWh. Those are project objectives, not completed refurbishment results.
Source: Nuclearelectrica stock-exchange filing, 16 November 2026.