By Energy People.
Perpetua Resources says power-pole installation for Idaho’s Stibnite Gold Project began in October, adding to work on access roads and worker accommodation outlined in its 13 November quarterly update.
Substations and transformers are on order, with poles and associated equipment being delivered to laydown areas in Donnelly and Cascade. The company also reports foundation installation for accommodation buildings and further work on the Burntlog access route.
Perpetua expects to close its proposed $2.9 billion US Export-Import Bank loan in the first quarter of 2027. The bank’s board approved the financing in May, but definitive documents and conditions still need to be completed before closing and funding.
The company says it is advancing engineering, procurement and critical-path construction ahead of a final investment and construction decision. It reported $443.4 million of unrestricted cash at 30 September. The update therefore records preparatory progress, rather than a new final investment decision or confirmed loan drawdown.
Image credit: Illustrative mining-equipment file photograph: QIT Euclid haul truck at Havre-Saint-Pierre, Québec, Canada, 19 June 2005. This is not Stibnite or Perpetua equipment. SyGrnwd / Wikimedia Commons, CC BY-SA 4.0. Resized; same licence retained.